Project Overview
Reconstruction of the State Street and Grand Avenue CTA subway station required excavation to depths of 42 feet, predominantly in very soft clays.
The existing streets are underlain by numerous utility lines and thus a soldier pile and lagging system was chosen, with the design allowing adjustment of final pile locations. Strut locations were chosen to minimize interference with wall, stairs, and floor construction. Ground movements were computed and compared to measured data throughout the project.